green trees in glass building

Hotel Ararat Park Hyatt, Moscow

The former Hilton Hotel, now the Ararat Park Hyatt Hotel in Moscow, has commissioned All Engineering to plan and carry out the electrical installations as part of a renovation project. All Engineering will also handle all approval management for the project.

  • Project: Hilton Hotel Moscow, city center
    Description: Complete planning of electrical installations. Complete execution of electrical installations, except for fire alarm system and low-voltage technology.

  • Project volume: 4.8 million DM

  • Start of construction: December 2000

  • Construction period: 11 months

  • Client: Hilton Hotel

  • General contractor: All Engineering

  • All Engineering contract: Complete planning, including approval planning and obtaining all approvals and acceptance reports.

  • Installation time: 10 months

  • Special features:
    The entire hotel had to be planned, approved, and installed in a very short time. Great importance was attached to design, which often led to changes in the plans. Flexibility and aesthetics were particularly important to the client in this project.